Importance:It will improve the quality of the road, attracting the flow of grain production. It aims to minimize investments and operating costs, in order to make it feasible, considering the expectation of Ferrogrão’s start of operations.
08/28/2019
Studies
05/14/2020
Public Hearing
12/17/2020
TCU
03/31/2021
Bidding Documents
07/08/2021
Public Auction
03/17/2022
Contract
estimated 28,635 (direct, indirect and income effect).
R$ 1,76 billion
R$ 1.01 billion
1.009 Km
10 years
VEQdiary: 34,3 thousand (Year 2)
lower fare
Via Brasil BR-163
R$ 0,07867
8.47%
Resolution No. 52 of May 8, 2019; Decree No. 9,972/2019.