PORTS - Solid Bulk lease at the Port of Aratu-Candeias/BA (ATU12)

PORTS - Solid Bulk lease at the Port of Aratu-Candeias/BA

Importance: According to data from the Master Plan of the Port of Aratu-Candeias, 1,837,323 t of solid bulk were handled in 2014, with emphasis on the landings of fertilizers (819,401 t) and copper concentrate (549,565 t). The projection is that by 2030 these cargoes will become the third main product handled in the port, increasing its market share to 14%. The port complex serves as a route for the flow of production and imports from the Industrial Complex of Camaçari – the largest integrated industrial complex in the Southern Hemisphere and its area of influence aggregates the states of Bahia, Sergipe, Alagoas and Pernambuco.

stage:

12/02/2019

Studies

03/30/2020

Public Hearing

08/05/2020

TCU

09/02/2020

Bidding Documents

12/18/2020

Public Auction

1st Trim 2021

Contract

UF:

Brownfield Project

Jobs created throughout the lease contract:

estimated 5.649 (direct, indirect and income effect)

Vocation:

Cargo - Solid Bulk Fertilizers

Terminal Area:

154.916 m²

Static capacity:

190.000/t

EXPECTED INVESTMENT:

R$ 244,95 million

Fixed monthly remuneration:

R$ 1,805.8 k

Variable Remuneration Value (R$/t):

R$ 9.75

LEASE TERM:

25 years

IRR:

9.38%.

AUCTION CRITERION:

Highest Grant

PPI QUALIFICATION:

Resolution Nº 69, of august 21, 2019.